Bradford Water Pollution Control Plant Expansion

 

 

Company
KENAIDAN GROUP
Facility Type
Waterworks
Location
225 Dissette Street, Bradford, ON
Start Date
01/2007
End Date
01/2009

 

 

PROJECT DESCRIPTION

The WPCP Expansion project included the addition of 4 new aeration tanks, 4 clarifiers, 2 biosolids storage tanks, a new digester, and a glass lined biosolids storage tank.

Additional structures included administration, headworks, raw sewage, filter, blower, and digester control buildings. The plant was built to meet the new effluent guidelines set by the Ministry of Environment because effluent was discharged into Lake Simcoe. Kenaidan self-performed the 26,100m² of formwork and the placement of 13,500m³ of concrete.

 

 

 

 