MnDOT St. Croix River Bridge Foundations, Oak Park Heights

 

 

Company
KRAEMER NORTH AMERICA
Facility Type
Dams/Power Plants
Location
Oak Park Heights, MN
Start Date
04/2013
End Date
01/2014

 

 

PROJECT DESCRIPTION

Kraemer constructed five river piers and foundations for the new St. Croix River extradosed bridge and developed an innovative precast cofferdam design by integrating elements of a traditional and deep water precast cofferdam. The hybrid substantially reduced the depth of the seals needed for the cofferdam. This innovation reduced the amount of excavation to be treated and disposed by more than 8,800 cubic yards. Despite challenging river conditions, Kraemer completed the project four months ahead of schedule.

 

 

 

 