Wisconsin Southern Rail Bridge Rehabilitation

 

 

Company
KRAEMER NORTH AMERICA
Facility Type
Roads/Tunnels/Bridges
Location
Sheboygan County, WI
Start Date
03/2015
End Date
07/2015

 

 

PROJECT DESCRIPTION

Kraemer rehabilitated three WSOR structures (Bridges 824, 826, and 841) over the Sheboygan and Mullet Rivers near Sheboygan Falls, WI and Plymouth, WI. Work included full removal of the existing timber trestle at the Plymouth location, construction of two new CIP pier caps founded on 36-inch diameter caissons and two new precast abutments founded on piling. The new structure is three-span steel beam bridge with a new timber tie deck and walkway. Steel bridge rehab work over the Sheboygan River included removal and replacement of existing bottom cover plates, stringer replacement, gusset and stiffener remove and replace, and remove-clean-replace existing bearings.

 

 

 

 