I-94 - MacKubin and Grotto St

 

 

Company
KRAEMER NORTH AMERICA
Facility Type
Roads/Tunnels/Bridges
Location
St Paul, MN
Start Date
05/2016
End Date
04/2017

 

 

PROJECT DESCRIPTION

Project includes two precast concrete girder and cast-in-place T girder Pedestrian Bridges over Interstate 94 in ST Paul, MN. Project also includes retaining wall approaches.

Project was started in Spring of 2016 and open to traffic in November of 2016. Punch list and final subcontract work such as painting and landscaping was completed in the Spring of 2017. 

 

 

 

 