Annacis Island WWTP Stage V Phase 1 Expansion - CDAC Building

 

 

Company
KENAIDAN GROUP
Facility Type
Waterworks
Location
Vancouver, BC, Canada
Start Date
04/2015
End Date
05/2017

 

 

PROJECT DESCRIPTION

The CDAC (Computerized Data Acquisition and Control) Administration Building is being constructed to provide permanent accommodations for programming staff as well as additional laboratory space required to process the increased volume of testing resulting from the Stage V expansion.

Initial demolition of the existing Chlorine Building was followed by construction of the new administration building. The building is a structural steel frame cladded with an aluminum composite panel system, utilizing five colours. Dedicated venting systems, low solar reflective glass, and exterior solar shading provide for enhanced interior temperature and air quality control.

The scope of work also included: utility relocation, re-alignment of Thickener Street, site services, utility connection from the existing WPE/IPS tunnel to the new CDAC building, and pile driving for the foundation work to meet the seismic requirements.

Photo by Kenaidan Contracting Ltd.

 

 

 

 

OTHER PROJECT ( ALL PROJECTS)